Petrofac submits lowest bid for Bahrain’s gas facility contract

nogaholding-bahrain

Bahrain’s Bapco Upstream has received bidders proposal for EPC of Non-Associated Gas (NAG) Compressor Facilities and associated works.

Three contractors including Petrofac, Arabian International Contracting, and TDE Overseas Ltd submitted proposals, out of which Petrofac’s bid was the lowest.

As per the tender notification, Tatweer Petroleum is undertaking a phased field development project to install Non-Associated Gas (NAG) Compressor Facilities (NCF’s) Stations and Remote Gas Dehydration Units (GDU) to maintain gas deliverability from the Awali field in Bahrain.

The scope of work defined under this Project is for EPC execution, keeping the future phases of development in sight when appropriate. Engineering, Procurement and Construction of Non-Associated Gas Well Hook-Ups, Associated Pipelines and Tie-ins at Compression & Gas Dehydration Facilities assisting with the operatability enhancement of Tatweer Petroleum facilities.